Which of the following statements is true about the MRP plan when using lot-for-lot ordering? |
| A. | The quantity of gross requirements for a child item is always equal to the quantity of planned order releases for its parent. |
| B. | The quantity of gross requirements for a child item is equal to the quantity of net requirements for its parent(s) multiplied by the number of child items used in the parent assembly. |
| C. | The quantity of gross requirements for a child item is always equal to the quantity of gross requirements for its parent. |
| D. | The quantity and gross requirements for a child item is always equal to the quantity of net requirements for its parent. |
| Answer» C. The quantity of gross requirements for a child item is always equal to the quantity of gross requirements for its parent. | |