1.

The quantity of coarse aggregate required for RCC (1:3:6) for 20 cubic metres of work is ________

A. 18.24 m<sup>3</sup>
B. 15.23 m<sup>3</sup>
C. 24.87 m<sup>3</sup>
D. 32.45 m<sup>3</sup>
Answer» B. 15.23 m<sup>3</sup>