It is estimated that an activity can be assigned an optimistic duration of 16 days, a pessimistic duration of 28 days and a most likely duration of 19 days. What is the expected duration for this activity? |
| A. | 20 days |
| B. | 19 days |
| C. | 22 days |
| D. | 18 days |
| Answer» B. 19 days | |