A float (or slack) in a critical path method (CPM) is amount of time that a task can be delayed without causing any delay to |
| A. | Subsequent tasks and project completion date |
| B. | Interdependent tasks |
| C. | Subsequent tasks only |
| D. | Preceding tasks |
| E. | Project completion date only |
| Answer» B. Interdependent tasks | |