| 1. |
Independent float is an amount of time by which the start of an activity may be delayed without affecting1. the preceding or the following activity2. the start of a following activity3. the completion of the project |
| A. | 1 only |
| B. | 2 only |
| C. | 3 only |
| D. | 1, 2 and 3 |
| Answer» E. | |