| 1. |
In project network analysis, which of the following statements is TRUE? |
| A. | All critical activities must join two critical events |
| B. | All activities joining two critical events are necessarily critical |
| C. | Some activities having non-zero floats can be critical |
| D. | Dummy activities can never become critical |
| Answer» B. All activities joining two critical events are necessarily critical | |