In PERT, If To and Tp are optimistic time and pessimistic time which an activity takes for its performance, then assumed standard deviation to measure uncertainty is taken as |
| A. | (To + Tp)/6 |
| B. | (4To + 2Tp)/6 |
| C. | (2To + 4Tp)/6 |
| D. | (Tp – To)/6 |