In a CPM network latest finish time for an event I is 8 weeks. Activity I-J takes 4 weeks for completion.Event J starts after 12 weeks. Float for activity I-J is |
| A. | 4 weeks |
| B. | 8 weeks |
| C. | 12 weeks |
| D. | 0 weeks |