If the optimistic time, most likely time and pessimistic time or activity A are 4, 6 and 8 weeks. Respectively and for activity B are 5, 5.5 and 9 weeks respectively, then |
| A. | Expected time of activity A is greater than the expected time of activity B |
| B. | Expected time of activity B is greater than the expected time of activity A |
| C. | Expected time of both activities A and B are same |
| D. | Data too inadequate to compute expected times of activities |
| Answer» D. Data too inadequate to compute expected times of activities | |