Duration along the critical path defines which of the following? A. Shortest duration needed B. Shortest duration permissible C. Longest duration needed D. Longest duration permissible Select the code for the correct answer from the options given below: |
| A. | A and B only |
| B. | A and D only |
| C. | B and C only |
| D. | C and D only |
| Answer» C. B and C only | |