This section includes 63 Mcqs, each offering curated multiple-choice questions to sharpen your Software Engg knowledge and support exam preparation. Choose a topic below to get started.
| 51. |
A construction company has an annual demand of 200 M / T. of steel, The annual cost of carrying per M. T. of steel is Es. 2000 and the cost of place an order is Rs. 50000. What is the economic order quantity? |
| A. | 50 M.T |
| B. | 70.7 M.T |
| C. | 100 M.T |
| D. | 40 M.T |
| Answer» D. 40 M.T | |
| 52. |
Certain key events in the life of a project are called: |
| A. | Dummies |
| B. | Critical events |
| C. | Nodes |
| D. | Milestones |
| Answer» E. | |
| 53. |
If the optimistic time, most likely time and pessimistic time or activity A are 4, 6 and 8 weeks. Respectively and for activity B are 5, 5.5 and 9 weeks respectively, then |
| A. | Expected time of activity A is greater than the expected time of activity B |
| B. | Expected time of activity B is greater than the expected time of activity A |
| C. | Expected time of both activities A and B are same |
| D. | Data too inadequate to compute expected times of activities |
| Answer» D. Data too inadequate to compute expected times of activities | |
| 54. |
SOFTWARE_PROJECT_ESTIMATION_CAN_NEVER_BE_AN_EXACT_SCIENCE,_BUT_A_COMBINATION_OF_GOOD_HISTORICAL_DATA_AND_SYSTEMATIC_TECHNIQUES_CAN_IMPROVE_ESTIMATION_ACCURACY.?$ |
| A. | True |
| B. | False |
| Answer» B. False | |
| 55. |
Which of the following is not achieved by an automated estimation tools? |
| A. | Predicting staffing levels |
| B. | Predicting software cost |
| C. | Predicting software schedules |
| D. | Predicting clients demands |
| Answer» E. | |
| 56. |
What can be used to complement decomposition techniques and offer a potentially valuable estimation approach in their own right? |
| A. | Automated estimation tools |
| B. | Empirical estimation models |
| C. | Decomposition techniques |
| D. | Both Automated estimation tools and Empirical estimation models |
| Answer» C. Decomposition techniques | |
| 57. |
Which of the following is not an option to achieve reliable cost and effort estimate? |
| A. | Base estimates on similar projects that have already been completed |
| B. | Use one or more empirical models for software cost and effort estimation |
| C. | Use relatively simple decomposition techniques to generate project cost and effort estimates |
| D. | The ability to translate the size estimate into human effort, calendar time, and dollars |
| Answer» E. | |
| 58. |
The environment that supports the software project is called |
| A. | CLSS |
| B. | SEE |
| C. | FAST |
| D. | CBSE |
| Answer» C. FAST | |
| 59. |
The project planner examines the statement of scope and extracts all important software functions which is known as |
| A. | Association |
| B. | Decomposition |
| C. | Planning process |
| D. | All of the mentioned |
| Answer» C. Planning process | |
| 60. |
CLSS stands for |
| A. | conveyor line sorting system |
| B. | conveyor line sorting software |
| C. | conveyor line sorting speed |
| D. | conveyor line sorting specification |
| Answer» B. conveyor line sorting software | |
| 61. |
A number of independent investigators have developed a team-oriented approach to requirements gathering that can be applied to establish the scope of a project called |
| A. | JAD |
| B. | CLASS |
| C. | FAST |
| D. | None of the mentioned |
| Answer» D. None of the mentioned | |
| 62. |
What describes the data and control to be processed? |
| A. | Planning process |
| B. | Software scope |
| C. | External hardware |
| D. | Project complexity |
| Answer» C. External hardware | |
| 63. |
Which of the following is an important factor that can affect the accuracy and efficacy of estimates? |
| A. | Project size |
| B. | Planning process |
| C. | Project complexity |
| D. | Degree of structural uncertainty |
| Answer» B. Planning process | |