| 1. |
The measurement is made for stone work in square metre in case of ________ |
| A. | Wall facing |
| B. | Columns, lintels, copings |
| C. | Footings |
| D. | Building work |
| Answer» B. Columns, lintels, copings | |
| 2. |
The floor area includes the area of the balcony up to _________ |
| A. | 50 % |
| B. | 60 % |
| C. | 70 % |
| D. | 45 % |
| Answer» B. 60 % | |
| 3. |
Referring to the figure below, pick up the correct statement from the following. |
| A. | The total length of centre line of four walls is 20 m |
| B. | Length of long wall out-to-out is 6.80 m |
| C. | Length of short walls in-to-in is 3.20 m |
| D. | Total length of four wall – 20 m, length of short wall – 6.8 m |
| Answer» E. | |
| 4. |
The ‘centre line method’ is specially adopted for estimating? |
| A. | Circular buildings |
| B. | Hexagonal buildings |
| C. | Other geometrical shaped buildings |
| D. | Circular, hexagonal and other geometric shapes |
| Answer» E. | |
| 5. |
The floor area includes the area of the balcony up to ________? |
| A. | 50 % |
| B. | 60 % |
| C. | 70 % |
| D. | 45 % |
| Answer» B. 60 % | |
| 6. |
The expected out turn of half brick partition wall per mason per day is _________ |
| A. | 1.5 m<sup>3</sup> |
| B. | 2.0 m<sup>3</sup> |
| C. | 4.0 m<sup>2</sup> |
| D. | 5.0 m<sup>2</sup> |
| Answer» B. 2.0 m<sup>3</sup> | |
| 7. |
The expected out turn for earth work in excavation in ordinary soil per labourer per day is _____ |
| A. | 1 cum |
| B. | 2 cum |
| C. | 3 cum |
| D. | 4 cum |
| Answer» E. | |
| 8. |
The total length of centre line of four walls is 20 m |
| A. | Length of long wall out-to-out is 6.80 m |
| B. | Length of short walls in-to-in is 3.20 m |
| C. | Total length of four wall – 20 m, length of short wall – 6.8 m |
| Answer» D. | |
| 9. |
The ‘centre line method’ is specially adopted for estimating?$ |
| A. | Circular buildings |
| B. | Hexagonal buildings |
| C. | Other geometrical shaped buildings |
| D. | Circular, hexagonal and other geometric shapes |
| Answer» E. | |
| 10. |
For the construction of buildings, the subheads of the estimate are ________ |
| A. | Earthwork, Concrete work, Brick work |
| B. | Plastering or pointing, finishing, water supply and sanitary work |
| C. | Brickwork Flooring, Wood work, Steel work |
| D. | Earthwork, concrete work, brick work, plastering, water supply and steel work |
| Answer» E. | |
| 11. |
For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is _______ |
| A. | 0.90 m<sup>3</sup> |
| B. | 0.94 m<sup>3</sup> |
| C. | 0.98 m<sup>3</sup> |
| D. | 0.98 m<sup>3</sup> |
| Answer» C. 0.98 m<sup>3</sup> | |