| 1. |
The expected out turn of half brick partition wall per mason per day is _________ |
| A. | 1.5 m<sup>3</sup> |
| B. | 2.0 m<sup>3</sup> |
| C. | 4.0 m<sup>2</sup> |
| D. | 5.0 m<sup>2</sup> |
| Answer» B. 2.0 m<sup>3</sup> | |