MCQOPTIONS
Saved Bookmarks
This section includes 27 Mcqs, each offering curated multiple-choice questions to sharpen your Prestressed Concrete Structures knowledge and support exam preparation. Choose a topic below to get started.
| 1. |
If the spans are large, they can be sub divided by means of ____________ |
| A. | Struts |
| B. | Piers |
| C. | Ridges |
| D. | Walls |
| Answer» C. Ridges | |
| 2. |
The construction procedure must be planned using ____________ |
| A. | Sequential computations |
| B. | Reverse computations |
| C. | Complicated computations |
| D. | Aligned computations |
| Answer» B. Reverse computations | |
| 3. |
What is the main feature of this method comprises a moveable temporary arrangement to limit? |
| A. | Feasible stress |
| B. | Cantilever stress |
| C. | Rigidity stress |
| D. | Bond stress |
| Answer» C. Rigidity stress | |
| 4. |
The construction starts at one end of the structure and proceeds continuously to the other end is? |
| A. | Progressive placement method |
| B. | Transverse placement method |
| C. | Horizontal placement method |
| D. | Linear placement method |
| Answer» B. Transverse placement method | |
| 5. |
In push out technique each unit in cast directly against the ____________ |
| A. | Previous unit |
| B. | Tensile unit |
| C. | Last units |
| D. | Progressive units |
| Answer» B. Tensile unit | |
| 6. |
The cantilever method has been successfully used in the span range of ____________ |
| A. | 40-150 |
| B. | 30-150 |
| C. | 50-200 |
| D. | 40-200 |
| Answer» D. 40-200 | |
| 7. |
In the cost insitu method the least time required to move formwork is? |
| A. | 7 |
| B. | 8 |
| C. | 3 |
| D. | 2 |
| Answer» B. 8 | |
| 8. |
The main advantage of using precast segmental units is they can be cast on ____________ |
| A. | Beam |
| B. | Slab |
| C. | Edges |
| D. | Ground |
| Answer» E. | |
| 9. |
One of the example of cast insitu construction. |
| A. | Boussens bridge, France |
| B. | Larens bridge, Uganda |
| C. | Lithcher bridge, Spain |
| D. | Rouli bridge, Africa |
| Answer» B. Larens bridge, Uganda | |
| 10. |
In cat insitu construction the formwork is supported by ____________ |
| A. | Aluminium frame work |
| B. | Wood frame work |
| C. | Steel frame work |
| D. | Cloth formwork |
| Answer» D. Cloth formwork | |
| 11. |
The major methods of cantilever construction are classified into how many types? |
| A. | 2 tyres |
| B. | 3 types |
| C. | 4 types |
| D. | 6 types |
| Answer» B. 3 types | |
| 12. |
Cantilever construction eliminates the use of ____________ |
| A. | Steel |
| B. | Cement |
| C. | Formwork |
| D. | Workman |
| Answer» D. Workman | |
| 13. |
IN_PUSH_OUT_TECHNIQUE_EACH_UNIT_IN_CAST_DIRECTLY_AGAINST_THE:?$ |
| A. | Previous unit |
| B. | Tensile unit |
| C. | Last units |
| D. | Progressive units |
| Answer» B. Tensile unit | |
| 14. |
The main feature of this method comprises a moveable temporary arrangement to limit the:$ |
| A. | Feasible stress |
| B. | Cantilever stress |
| C. | Rigidity stress |
| D. | Bond stress |
| Answer» C. Rigidity stress | |
| 15. |
The construction starts at one end of the structure and proceeds continuously to other end is:$ |
| A. | Progressive placement method |
| B. | Transverse placement method |
| C. | Horizontal placement method |
| D. | Linear placement method |
| Answer» B. Transverse placement method | |
| 16. |
If the spans are large, they can be sub divided by means of: |
| A. | Struts |
| B. | Piers |
| C. | Ridges |
| D. | Walls |
| Answer» C. Ridges | |
| 17. |
In incremental launching or pull out technique to allow the super structure to move forward, what are provided? |
| A. | Sliding bearings |
| B. | Rolling bearings |
| C. | Strut bearings |
| D. | Tensile bearings |
| Answer» B. Rolling bearings | |
| 18. |
The construction procedure must be planned using: |
| A. | Sequential computations |
| B. | Reverse computations |
| C. | Complicated computations |
| D. | Aligned computations |
| Answer» B. Reverse computations | |
| 19. |
Which type of construction is particularly advantageous in long via duct structures, a segmental? |
| A. | Span to span |
| B. | Edge to edge |
| C. | Column to column |
| D. | Beam to beam |
| Answer» B. Edge to edge | |
| 20. |
Which one of the following method of construction is adopted when low clearance is required below the deck? |
| A. | Erection method |
| B. | Stagging method |
| C. | Elongation method |
| D. | Longitudinal method |
| Answer» C. Elongation method | |
| 21. |
The cantilever method has been successfully used in the span range of: |
| A. | 40-150 |
| B. | 30-150 |
| C. | 50-200 |
| D. | 40-200 |
| Answer» D. 40-200 | |
| 22. |
In the cost insitu method the least time required to move formwork is: |
| A. | 7 |
| B. | 8 |
| C. | 3 |
| D. | 2 |
| Answer» B. 8 | |
| 23. |
The main advantage of using precast segmental units is they can be cast on: |
| A. | Beam |
| B. | Slab |
| C. | Edges |
| D. | Ground |
| Answer» E. | |
| 24. |
One of the example of cast insitu construction: |
| A. | Boussens bridge, France |
| B. | Larens bridge, Uganda |
| C. | Lithcher bridge, Spain |
| D. | Rouli bridge, Africa |
| Answer» B. Larens bridge, Uganda | |
| 25. |
In cat insitu construction the formwork is supported by: |
| A. | Aluminium frame work |
| B. | Wood frame work |
| C. | Steel frame work |
| D. | Cloth formwork |
| Answer» D. Cloth formwork | |
| 26. |
The major methods of cantilever construction are classified into how many types: |
| A. | 2 tyres |
| B. | 3 types |
| C. | 4 types |
| D. | 6 types |
| Answer» B. 3 types | |
| 27. |
Cantilever construction eliminates the use of: |
| A. | Steel |
| B. | Cement |
| C. | Formwork |
| D. | Workman |
| Answer» D. Workman | |