MCQOPTIONS
Saved Bookmarks
This section includes 61 Mcqs, each offering curated multiple-choice questions to sharpen your Concrete Technology knowledge and support exam preparation. Choose a topic below to get started.
| 51. |
“ISO 9001 standard measures and recognizes the quality of a company’s products”. This statement is: |
| A. | False |
| B. | Maybe |
| C. | True |
| D. | None of these |
| Answer» D. None of these | |
| 52. |
THE_PROPERTY_OF_A_MATERIAL_THAT_RESISTS_PENETRATION_OR_INDENTATION_BY_MEANS_OF_ABRASION_OR_SCRATCHING_IS_KNOWN_AS_____________?$ |
| A. | Strength |
| B. | Hardness |
| C. | Stiffness |
| D. | Toughness |
| Answer» C. Stiffness | |
| 53. |
During_compression_test_of_cast_iron,_the_failure_occurs_i.e._the_crack_appears_along_the___________$ |
| A. | Diagonal |
| B. | Surface parallel to load applied |
| C. | Surface perpendicular to load applied |
| D. | Lateral |
| Answer» B. Surface parallel to load applied | |
| 54. |
It opens the area of improvement for quality construction rationally based on the documents from ___________ projects? |
| A. | Previous |
| B. | Next |
| C. | Later |
| D. | Future |
| Answer» B. Next | |
| 55. |
Quality management system improves perception of customers towards company. True or false |
| A. | True |
| B. | False |
| Answer» B. False | |
| 56. |
___________ quality construction ___________ the wastage of materials. |
| A. | Good, reduce |
| B. | Bad, reduce |
| C. | Good, increase |
| D. | Bad, Decrease |
| Answer» B. Bad, reduce | |
| 57. |
It __________ job-site concrete handling, and testing procedures to __________ potential liability to the company. |
| A. | Improve, Increase |
| B. | Improve, Decrease |
| C. | Ruin, Decrease |
| D. | Ruin, Increase |
| Answer» C. Ruin, Decrease | |
| 58. |
___________ cost of maintenance of the structure __________ construction due to quality works. |
| A. | Maximize, after |
| B. | Minimize, after |
| C. | Maximize, before |
| D. | Minimize, before |
| Answer» C. Maximize, before | |
| 59. |
Quality control helps to ____________ the risks of overdesign that ___________ the overall cost. |
| A. | Maximize, Increase |
| B. | Minimize, Increase |
| C. | Maximize, Decrease |
| D. | Minimize, Decrease |
| Answer» E. | |
| 60. |
The basic requirement for the success of any quality control plan is the availability of experienced, knowledgeable and trained personnel at all the levels. True or False. |
| A. | True |
| B. | False |
| Answer» B. False | |
| 61. |
For walls, columns and vertical faces of all structural members, the form work is generally removed after |
| A. | 24 to 48 hours |
| B. | 3 days |
| C. | 7 days |
| D. | 14 days |
| Answer» B. 3 days | |