You have just completed Qualitative Risk Analysis of the project. What should you be doing next? |
| A. | Plan Risk Management |
| B. | Perform Quantitative Risk Analysis |
| C. | Plan Risk Responses |
| D. | Control Risks |
| Answer» C. Plan Risk Responses | |