MCQOPTIONS
Saved Bookmarks
| 1. |
With reference to project management, identify which of the following statement is NOT correct? |
| A. | Gantt chart is a principal tool used in scheduling and also in some methods of loading. |
| B. | Routing is the first step in the production planning. |
| C. | The cost of any activity is proportional to its time of completion. |
| D. | The free float can be calculated by subtracting EFT from EST. |
| Answer» E. | |