MCQOPTIONS
Saved Bookmarks
| 1. |
The time corresponding to minimum total project cost is_______________? |
| A. | crash time |
| B. | normal time |
| C. | optimistic time |
| D. | between normal time and crash time |
| Answer» E. | |