In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________? |
| A. | longest duration |
| B. | highest cost slope |
| C. | least cost slope |
| D. | shortest duration |
| Answer» D. shortest duration | |