| 1. |
In the critical path method of construction planning, Free Float can be_____________?_x005F_x000D_Consider the following statements ?_x005F_x000D_1. greater than Total Float._x005F_x000D_2. greater than Independent Float_x005F_x000D_3. equal to Total Float._x005F_x000D_4. less than Independent Float. Of these statements |
| A. | 1 and 4 are correct |
| B. | 2 and 3 are correct |
| C. | 1 and 4 are correct |
| D. | 1 and 2 are correct |
| Answer» C. 1 and 4 are correct | |