In PERT analysis, the time estimates of activities and probability of their occurrence follow_______________? |
| A. | normal distribution curve |
| B. | Poisson’s distribution curve |
| C. | Beta – distribution curve |
| D. | none of the above |
| Answer» D. none of the above | |