For normal M 20 reinforced concrete, the minimum time of removing the props of form work for slabs with spans less than 4.5 m is |
| A. | 21 days |
| B. | 3 days |
| C. | 7 days |
| D. | 28 days |
| Answer» D. 28 days | |