| 1. |
Fifteen men take 10 days to complete a job working 12 hours a day. How many hours a day should 10 men work to complete the job in 20 days? |
| A. | 7 |
| B. | 8 |
| C. | 9 |
| D. | 11 |
| Answer» D. 11 | |