_______________ estimate is a detailed estimate and is prepared to maintain the structure or work in proper order and safe condition. |
| A. | Supplementary and revised estimate |
| B. | Maintenance estimate |
| C. | Item rate estimate |
| D. | Revised estimate |
| Answer» C. Item rate estimate | |