| 1. |
Economic saving of time results by crashing_________________? |
| A. | cheapest critical activity |
| B. | cheapest non-critical activity |
| C. | costliest critical activity |
| D. | costliest non-critical activity |
| Answer» B. cheapest non-critical activity | |