Critical path
1.
Critical path
A.
Is always longest
B.
Is always shortest
C.
May be longest
D.
May be shortest
Answer» B. Is always shortest
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel.
A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively
Latest start of an activity is always
Earliest finish of an activity is always
Critical path
In time-cost optimization of a project, crashing is done.
CPM is
The most popular type of organization used for Civil Engineering Constructions, is