Critical path_____________?
1.
Critical path_____________?
A.
is always longest
B.
is always shortest
C.
may be longest
D.
may be shortest
Answer» B. is always shortest
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
Which one of the following is not an excavating and moving type of equipment ?
Which of the following is not a PERT event ?
Which of the following is a weakness of bar chart ?
Whenever an activity has zero total float, then_______________?
Wheeled tractors are replacing crawler tractors because________________?_x005F_x000D_Consider the following statements?_x005F_x000D_1. wheeled tractors travel faster_x005F_x000D_2. crawler tractors are more expensive_x005F_x000D_3. track parts of a crawler wear out quickly_x005F_x000D_4. crawler tractors have stick control
Updating may result in_________________?
Total float for any activity is defined as the difference between________________?
The time with which direct cost does not reduce with the increase in time is known as_________________?
The time corresponding to minimum total project cost is_______________?
The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as_______________?