| 1. |
HOW_ARE_BASELINES_VERIFIED??$ |
| A. | By reviews |
| B. | By inspections |
| C. | By testing of code |
| D. | All of the mentioned |
| Answer» D. All of the mentioned | |
| 2. |
SCM controls only the products of the development process.$ |
| A. | True |
| B. | False |
| Answer» B. False | |
| 3. |
Which of the following is a example of Configuration Items ?$ |
| A. | SCM procedures |
| B. | Source code |
| C. | Software design descriptions |
| D. | All of the mentioned |
| Answer» E. | |
| 4. |
What information is required to process a change to a baseline? |
| A. | Reasons for making the changes |
| B. | A description of the proposed changes |
| C. | List of other items affected by the changes |
| D. | All of the mentioned |
| Answer» E. | |
| 5. |
CCB stands for |
| A. | Change Control Board |
| B. | Change Control Baseline |
| C. | Cumulative Changes in Baseline |
| D. | None of the mentioned |
| Answer» B. Change Control Baseline | |
| 6. |
What is one or more software configuration items that have been formally reviewed and agreed upon and serve as a basis for further development? |
| A. | Baseline |
| B. | Cumulative changes |
| C. | CM |
| D. | Change Control |
| Answer» B. Cumulative changes | |
| 7. |
Configuration management (CM) is needed to deliver product to the client |
| A. | True |
| B. | False |
| Answer» B. False | |
| 8. |
Which of the following is not a change management process? |
| A. | Log the changes |
| B. | Estimate impact on effort and schedule |
| C. | Review impact with stakeholders |
| D. | None of the mentioned |
| Answer» E. | |
| 9. |
What allows different projects to use the same source files at the same time? |
| A. | Version Control |
| B. | Access control |
| C. | CM Process |
| D. | Version Control and Access control |
| Answer» B. Access control | |
| 10. |
CM is about managing the different items in the product, and changes in them. |
| A. | True |
| B. | False |
| Answer» B. False | |
| 11. |
Which of the following is not a main phase in Configuration Management (CM) Process? |
| A. | CM Planning |
| B. | Executing the CM process |
| C. | CM audits |
| D. | None of the mentioned |
| Answer» E. | |
| 12. |
When code is made available to others, it goes in a/an |
| A. | hard drive |
| B. | access-controlled library |
| C. | servers |
| D. | access control |
| Answer» C. servers | |
| 13. |
SCM stands for |
| A. | Software Control Management |
| B. | Software Configuration Management |
| C. | Software Concept Management |
| D. | None of the mentioned |
| Answer» C. Software Concept Management | |