| 51. |
Which of the following is not one of the five information domain characteristics of Function Point (FP) decomposition? |
| A. | External inputs |
| B. | External outputs |
| C. | External process |
| D. | External inquiries |
| Answer» D. External inquiries | |
| 52. |
The project planner must reconcile the estimates based on decomposition techniques to produce a single estimate of effort. |
| A. | True |
| B. | False |
| C. | Can't say |
| D. | None of the above |
| Answer» C. Can't say | |
| 53. |
ACT stands for? |
| A. | Annual component traffic |
| B. | Apply component traffic |
| C. | Annual change track |
| D. | Annual change traffic |
| Answer» E. | |
| 54. |
Programming language experience is a part of which factor of COCOMO cost drivers? |
| A. | Personnel Factor |
| B. | Product Factor |
| C. | Platform Factor |
| D. | Project Factor |
| Answer» B. Product Factor | |
| 55. |
Software project management comprises of a number of activities, which contains _________. |
| A. | Project planning |
| B. | Scope management |
| C. | Project estimation |
| D. | All mentioned above |
| Answer» E. | |
| 56. |
Effective software project management focuses on the four P’s. What are those four P’s? |
| A. | People, performance, payment, product |
| B. | People, product, process, project |
| C. | People, product, performance, project |
| D. | All of the above |
| Answer» C. People, product, performance, project | |
| 57. |
Which tools are used in implementation,testing and maintenance? |
| A. | Upper case tools |
| B. | Integrated case tools |
| C. | Lower case tools |
| D. | None of the above |
| Answer» D. None of the above | |
| 58. |
The always growing and adapting nature of software hugely depends upon the environment in which user works in ____________ . |
| A. | Cost |
| B. | Dynamic Nature |
| C. | Quality Management |
| D. | Scalability |
| Answer» C. Quality Management | |
| 59. |
When the customer may ask for new features or functions in the software, what does it mean in Software maintenance? |
| A. | Host modifications |
| B. | Client requirements |
| C. | Market conditions |
| D. | Organization changes |
| Answer» C. Market conditions | |
| 60. |
Which Software-end factors affecting maintenance Cost? |
| A. | Structure of Software Program |
| B. | Programming Language |
| C. | Dependence on external environment |
| D. | All mentioned above |
| Answer» E. | |
| 61. |
Lehman has given eight laws for software evolution and he divided software into three categories. In which category software works strictly according to defined specifications and solutions. |
| A. | Static-type |
| B. | Embedded-type |
| C. | Practical-type |
| D. | None of the above |
| Answer» C. Practical-type | |
| 62. |
What is used for implementing the changes in existing or new requirements of user in software maintenance? |
| A. | Preventive maintenance |
| B. | Perfective maintenance |
| C. | Corrective maintenance |
| D. | Adaptive maintenance |
| Answer» C. Corrective maintenance | |
| 63. |
Give the Real-world factors affecting maintenance Cost. |
| A. | As technology advances, it becomes costly to maintain old software. |
| B. | The standard age of any software is considered up to 10 to 15 years. |
| C. | Most maintenance engineers are newbie and use trial and error method to rectify problem. |
| D. | All mentioned above |
| Answer» E. | |
| 64. |
Software project management is the process of managing all activities that are involved in software development, they are _____ . |
| A. | Time |
| B. | Cost |
| C. | Quality management |
| D. | All mentioned above |
| Answer» E. | |
| 65. |
THE_DEFINITION_AND_USE_OF_CONFIGURATION_MANAGEMENT_STANDARDS_IS_ESSENTIAL_FOR_QUALITY_CERTIFICATION_IN?$ |
| A. | ISO 9000 |
| B. | CMM |
| C. | CMMI |
| D. | All of the mentioned |
| Answer» E. | |
| 66. |
What involves preparing software for external release and keeping track of the system versions that have been released for customer use?$ |
| A. | System building |
| B. | Release management |
| C. | Change management |
| D. | Version management |
| Answer» C. Change management | |
| 67. |
Which of the following is not a Software Configuration Management Activity? |
| A. | Configuration item identification |
| B. | Risk management |
| C. | Release management |
| D. | Branch management |
| Answer» C. Release management | |
| 68. |
Which of the following option is not tracked by configuration management tools? |
| A. | Tracking of change proposals |
| B. | Storing versions of system components |
| C. | Tracking the releases of system versions to customers |
| D. | None of the mentioned |
| Answer» E. | |
| 69. |
Which of the following is the process of assembling program components, data, and libraries, and then compiling and linking these to create an executable system? |
| A. | System building |
| B. | Release management |
| C. | Change management |
| D. | Version management |
| Answer» B. Release management | |
| 70. |
What complements the formal technical review by assessing a configuration object for characteristics that are generally not considered during review? |
| A. | Software configuration audit |
| B. | Software configuration management |
| C. | Baseline |
| D. | None of the mentioned |
| Answer» B. Software configuration management | |
| 71. |
What combines procedures and tools to manage different versions of configuration objects that are created during the software process? |
| A. | Change control |
| B. | Version control |
| C. | SCIs |
| D. | None of the mentioned |
| Answer» C. SCIs | |
| 72. |
Software Configuration Management can be administered in several ways. These include |
| A. | A single software configuration management team for the whole organization |
| B. | A separate configuration management team for each project |
| C. | Software Configuration Management distributed among the project members |
| D. | All of the mentioned |
| Answer» B. A separate configuration management team for each project | |
| 73. |
Which is a software configuration management concept that helps us to control change without seriously impeding justifiable change? |
| A. | Baselines |
| B. | Source code |
| C. | Data model |
| D. | None of the mentioned |
| Answer» B. Source code | |
| 74. |
Which of the following categories is part of the output of software process? |
| A. | computer programs |
| B. | documents that describe the computer programs |
| C. | data |
| D. | all of the mentioned |
| Answer» E. | |