| 151. |
Probabilistic time for completion of any activity can be found out from |
| A. | optimistic time |
| B. | pessimistic time |
| C. | most likely time |
| D. | all of these |
| Answer» E. | |
| 152. |
Which one of the following chart gives simultaneously information about the progress of work and machine loading? |
| A. | Process chart |
| B. | Machine load chart |
| C. | Man-machine chart |
| D. | Gantt chart |
| Answer» D. Gantt chart | |
| 153. |
In a network shown in the below figure, the critical path is along |
| A. | 1-2-3-4-8-9 |
| B. | 1-2-3-5-6-7-8-9 |
| C. | 1-2-3-4-7-8-9 |
| D. | 1-2-5-6-7-8-9 |
| Answer» C. 1-2-3-4-7-8-9 | |
| 154. |
When slack of an activity is negative |
| A. | it represents a situation where extra resources are available and the completion of project is not delayed |
| B. | it represents that a programme falls behind schedule and additional resources are required to complete the project in time |
| C. | the activity is critical and any delay in its performance will delay the completion of whole project |
| D. | all of the above |
| Answer» C. the activity is critical and any delay in its performance will delay the completion of whole project | |
| 155. |
Work sampling is applied for |
| A. | estimation of the percentage utilisation of machine tools |
| B. | estimating the percentage of the time consumed by various job activities |
| C. | finding out time standards, specially where the job is not repetitive and where time study by stop watch method is not possible |
| D. | all of the above |
| Answer» E. | |
| 156. |
A systematic job improvement sequence will consist of |
| A. | motion study |
| B. | time study |
| C. | job enrichment |
| D. | all of these |
| Answer» E. | |
| 157. |
In inventory control theory, the economic order quantity is |
| A. | average level of inventory |
| B. | optimum lot size |
| C. | capacity of a warehouse |
| D. | lot size corresponding to break-even analysis |
| Answer» C. capacity of a warehouse | |
| 158. |
In value engineering, the term value refers to |
| A. | manufacturing cost of the product |
| B. | selling price of the product |
| C. | total cost of the product |
| D. | utility of the product |
| Answer» E. | |
| 159. |
The main object of scientific layout is |
| A. | to produce better quality of product |
| B. | to utilise maximum floor area |
| C. | to minimise production delays |
| D. | all of these |
| Answer» E. | |
| 160. |
Gantt chart is used for |
| A. | inventory control |
| B. | material handling |
| C. | production schedule |
| D. | machine repair schedules |
| Answer» D. machine repair schedules | |
| 161. |
In time study, the rating factor is applied to determine |
| A. | standard time of a job |
| B. | merit rating of the worker |
| C. | fixation of incentive rate |
| D. | normal time of a worker |
| Answer» E. | |
| 162. |
The aim of value engineering is to |
| A. | find the depreciation value of a machine |
| B. | determine the selling price of a product |
| C. | minimise the cost without change in quality of the product |
| D. | all of the above |
| Answer» D. all of the above | |