| 1. |
Which of the following layouts is suited for mass production? |
| A. | Process layout |
| B. | Product layout |
| C. | Fixed position layout |
| D. | Plant layout |
| Answer» C. Fixed position layout | |
| 2. |
Which of the following is independent of sales forecast? |
| A. | Productivity |
| B. | Inventory control |
| C. | Production planning |
| D. | Production control |
| Answer» B. Inventory control | |
| 3. |
For a product layout the material handling equipment must |
| A. | Have full flexibility |
| B. | Employ conveyor belts, trucks, tractors etc. |
| C. | Be a general purpose type |
| D. | Be designed as special purpose for a particular application |
| Answer» E. | |
| 4. |
The unit cost in case of batch production is __________as compared to jobbing production. |
| A. | Same |
| B. | Low |
| C. | High |
| D. | None of these |
| Answer» C. High | |
| 5. |
Basic tool in work study is |
| A. | Graph paper |
| B. | Process chart |
| C. | Planning chart |
| D. | Stop watch |
| Answer» E. | |
| 6. |
The allowed time for a job equals standard time plus |
| A. | Policy allowance |
| B. | Interference allowance |
| C. | Process allowance |
| D. | Learning allowance |
| Answer» B. Interference allowance | |
| 7. |
Tick the odd man out |
| A. | Taylor |
| B. | Drucker |
| C. | McGregor |
| D. | Galileo |
| Answer» E. | |
| 8. |
Which of the following organisation is preferred in automobile industry? |
| A. | Functional organisation |
| B. | Line organisation |
| C. | Staff organisation |
| D. | Line and staff organizations |
| Answer» E. | |
| 9. |
Work study is concerned with |
| A. | Improving present method and finding standard time |
| B. | Motivation of workers |
| C. | Improving production capability |
| D. | Improving production planning and control |
| Answer» B. Motivation of workers | |
| 10. |
An event is indicated on the network by |
| A. | A straight line |
| B. | A number enclosed in a circle or a square |
| C. | A straight line with circles at the ends |
| D. | A dotted line |
| Answer» C. A straight line with circles at the ends | |
| 11. |
Work study involves |
| A. | Only method study |
| B. | Only work measurement |
| C. | Method study and work measurement |
| D. | Only motion study |
| Answer» D. Only motion study | |
| 12. |
What does symbol 'O' imply in work study? |
| A. | Operation |
| B. | Inspection |
| C. | Transport |
| D. | Delay/temporary storage |
| Answer» B. Inspection | |
| 13. |
In which of the following layouts, the lines need to the balanced |
| A. | Process layout |
| B. | Product layout |
| C. | Fixed position layout |
| D. | Plant layout |
| Answer» C. Fixed position layout | |
| 14. |
Work study comprises following main techniques |
| A. | Method study and work measurement |
| B. | Method study and time study |
| C. | Time study and work measurement |
| D. | Method study and job evaluation |
| Answer» B. Method study and time study | |
| 15. |
Father of time study was |
| A. | F.W. Taylor |
| B. | H.L. Gantt |
| C. | F.B. Gilbert |
| D. | R.M. Barnes |
| Answer» B. H.L. Gantt | |
| 16. |
The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as |
| A. | Event |
| B. | Free float |
| C. | Artificial |
| D. | Dummy |
| Answer» E. | |
| 17. |
Pick up the incorrect statement from the following. A critical ratio scheduling |
| A. | Establishes the relative priorities among various activities on a common basis |
| B. | Determines the status of each activity |
| C. | Adjusts automatically changes in activity progress |
| D. | None of the above |
| Answer» E. | |
| 18. |
The reasons which are basically responsible for the formation of a queue should be that |
| A. | The average service rate Hess than the average arrival rate |
| B. | Output rate is linearly proportional to input |
| C. | Output rate is constant and the input varies in a random manner |
| D. | All of the above |
| Answer» E. | |
| 19. |
The basic difference between PERT and CPM is that |
| A. | PERT deals with events and CPM with activities |
| B. | Critical path is determined in PERT only |
| C. | Costs are considered on CPM only and not in PERT |
| D. | Guessed times are used in PERT and evaluated times in CPM |
| Answer» E. | |