X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work? |
| A. | $13\frac{1}{3}$$days |
| B. | 5 days |
| C. | 0 days |
| D. | 6 days |
| Answer» B. 5 days | |