1.

X can do \[1/4\] of a work in 10 days. Y Can do 40% of the work in 40 days and Z can do 1/3 of the work in 13 days. Who will complete the work first?

A.  X                                
B.  Y              
C.  Z       
D.  X and Z both
Answer» D.  X and Z both