| 1. |
Work done by A in one day is half of the work done by B in one day. Work done by B is half of the work done by C in one day. If C alone can complete the work in 7 days, in how many days can A, B and C together complete the work ? |
| A. | days |
| B. | 4 days |
| C. | 1 days |
| D. | 8 days |
| E. | one of these |
| Answer» B. 4 days | |