While scheduling a project by C.P.M. |
| A. | The difference between the earliest finish time of an activity and the earliest start time of its successor activity, is called free float of the activity |
| B. | None of these. |
| C. | a project is divided into various activities |
| D. | required time for each activity is established |
| Answer» E. | |