1.

Which of the following is true for project evaluation and review technique (PERT)?

A. It is even oriented and is a tool for planning
B. It is activity oriented and extensively used in construction
C. It uses cost as a critical input factor
D. It minimizes the importance of events
E. The events in such a network do not fall in logical sequence
Answer» B. It is activity oriented and extensively used in construction