Which of the following does not apply to agility to a software process? |
| A. | uses incremental product delivery strategy |
| B. | only essential work products are produced |
| C. | eliminate the use of project planning and testing |
| D. | all of the mentioned |
| Answer» D. all of the mentioned | |