| 1. |
Which of the following chart will indicate only the cumulative workloads for each job and to what extent the work centers are to be scheduled? |
| A. | Flowchart |
| B. | Gantt chart |
| C. | Gantt progress chart |
| D. | CPM chart |
| Answer» C. Gantt progress chart | |