| 1. |
Which of the following attempts are made to reduce the uplift in order to economize on the provided section of a concrete gravity dam?i. Providing drainage gallery to collect seepage waterii. Constructing cut-off under upstream faceiii. Pressure grouting in dam foundationiv. Provision of shear keys or keyways |
| A. | i and ii |
| B. | i, ii and iii |
| C. | i, ii and iv |
| D. | i, ii, iii and iv |
| Answer» C. i, ii and iv | |