Which is the correct sequence of jobs in construction management? |
| A. | Planning, Scheduling & Controlling |
| B. | Planning, Controlling & Scheduling |
| C. | Scheduling, Planning & Controlling |
| D. | Controlling, Planning & Scheduling |
| Answer» B. Planning, Controlling & Scheduling | |