When calculating cost variances under a standard costing system we must: |
| A. | Compare standard costs with actual costs at the standard level of activity |
| B. | Compare actual costs with those that were budgeted |
| C. | Compare actual costs with standard costs at the actual level of output |
| D. | Compare actual outputs against budgeted outputs |
| Answer» E. | |