What would be the critical path if the duration of...
1.
What would be the critical path if the duration of activity C increased to 10?
A.
ABCF
B.
ABCEF
C.
ABGHIF
D.
ABGHIF & ABDEF
Answer» B. ABCEF
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
Fishbone diagram
Additional working capital is
financial leverage is
following is not a ficed income bearing security
(NPBIT ÷ capital employed ) X 1000
Cultural implications of the project are examined by
Training requirement is a
functional type of structure is divided into department based on
A project is anything which is
Which of the following is not a characteristic of conflict?
Reply to Comment
×
Name
*
Email
*
Comment
*
Submit Reply
Your experience on this site will be improved by allowing cookies. Read
Cookie Policy
Reject
Allow cookies