Two persons, A and B together can do a piece of work in 15 days. B is 80% as efficient as A. Quantity I :If they work on alternate day, starting with A then how many days will they take to complete 50% of the work? Quantity II :How many days, B alone will take to complete 40% of the total work? |
| A. | Quantity : I > Quantity : II |
| B. | Quantity : I ≥ Quantity : II |
| C. | Quantity : I < Quantity : II |
| D. | Quantity : II ≥ Quantity : I |
| E. | Quantity I = Quantity II or relation can't be established |
| Answer» B. Quantity : I ≥ Quantity : II | |