MCQOPTIONS
Saved Bookmarks
| 1. |
Total Material cost variance = |
| A. | Standard cost of materials-actual cost of materials |
| B. | Budgeted cost of materials- actual cost of materials |
| C. | Standard cost of materials-budgeted cost of materials |
| D. | Actual cost of materials- budgeted cost of materials |
| Answer» B. Budgeted cost of materials- actual cost of materials | |