| 1. |
To get to labour efficiency variance, the formula to be applied is |
| A. | Total standard labour cost of actual output - Total actual cost of actual output |
| B. | (Standard rate per hour - Actual rate per hour) * Actual Hours |
| C. | (Standard time - Actual time) * Standard rate per hour |
| D. | Abnormal idle hours * Standard hourly rate |
| Answer» D. Abnormal idle hours * Standard hourly rate | |