To complete an assignment in 4 days, we need either 12 men or 15 women. 6 men take the project but stop working after 2 days. How many women will be required to finish the remaining work in 3 days? |
| A. | 15 |
| B. | 18 |
| C. | 22 |
| D. | 27 |
| Answer» B. 18 | |