The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days? |
| A. | 4 days |
| B. | 3 days |
| C. | 2 days |
| D. | 1 day |
| Answer» E. | |