1.

The project activities, precedence relationships and durations are described in thetable. The critical path of the project isActivityPrecedenceDuration (in days)P-3Q-4RP5SQ5TR, S7UR, S5VT2WU10

A. P-R-T-V
B. Q-S-T-V
C. P-R-U-W
D. Q-S-U-W
Answer» E.