1.

The primary reason why an open-circuit test is performed on the low-voltage winding of a transformer is that it:

A. draws sufficiently large on-load current for convenient reading
B. involves less core loss
C. needs minimum power input
D. requires least voltage to perform the test
Answer» B. involves less core loss