1.

The peak load on a power plant is 60 MW. The loads having maximum demands of 30 MW, 20 MW, 10 MW and 15 MW are connected to the power plant. Find the diversity factor.

A. 1.11
B. 0.9
C. 1.25
D. 0.8
Answer» D. 0.8